And we're off and racing!

To say the least, it's taken some time but we've finally been given the nod from Crown Lands for the sub-lease! Now that's squared away we can start ripping in, in earnest.

 

April Update

The slow wheels of progress

Well, to say the least, the last couple of months have not gone to plan. Firstly, the rain delayed the opening of the mini golf as we couldn't get enough sunny days to finish off the build. Our DA was rejected by Newcastle Council due to the Crown Lands permission not being sufficient to satisfy the Land Owners Consent provision (back through the Crown Lands hoops for a couple of months). And to top it all off, there was a requirement to prove to Council that the Mini Golf area was not a Flood Control Lot and therefore didn't need a separate DA to finish off the build. The joys of trying to start up a new business!

We're now slicing through the last reams of red tape and hope (Newcastle Council permitting) to have the DA in our hands at the end of April/early May. We've resumed the build of the Mini Golf, although the weather is still playing havoc with that, and plan to have that part of the facility ready for mid to late May.

We expect to start the internal build work immediately following the DA approval that will enable the indoor simulators to commence by the end of May as well. The driving range will take a little longer due to the importation of the netting structure ​but if the planets line up for us for a change, this should still be in June.

December Update

It's been a while...

Where to start? How about - we're nearly open! The mini golf course is well underway and our civil works machine, Goran, assures me that we're going to be open on Boxing Day with a few days to spare. Looking at the amount of work yet to be done I'm scratching my head as to how he's going to pull it off but he knows his stuff and hasn't let me down so far. 

The new roof is on and the 'indoor slip and slide' from all the leaks is no more
​ - thank you to Aaron Simcoe from Seaside Roof and Gutter for the great work. It was a great relief to get that sorted out.

The DA for the driving range and the works in the Auditorium was submitted mid-November and while we expect to see that come out the other end of January we cracked on with getting the architecturals and design elements lined up to go to tender. Catalyst Project Management have proved a Godsend, could not have managed this undertaking without them. Not only have they shouldered the load in progressing the project but they knew the right people to talk to and when they needed a tap on the shoulder.

 

So, hope to see the majority of Newcastle at the new mini golf facility on Boxing Day!!!

The new simulators inside the auditorium are now not far away either!

UPDATE TO THE UPDATE! The Mini Golf had slipped a few days due to the amount of rain we had through early December and then... close contacts for Covid struck the team working on the build. Unfortunately, we've had to make the call to delay opening until early in January to ensure everyone's safety. When we have a better picture of when we will be opening we will repost.

September Update

Out of the blocks.

Right, the first job in the barrel is to replace the roofing over the auditorium. As much as the tarpaulin rig for the leaky roof (see the May update further down) is a thing of rare beauty, it's not going to hang on much longer. Replacing the roofing will stabilise the damage to the auditorium's internals and enable the construction of the teaching and fitting bays.

We've also appointed Catalyst Project Consulting to direct traffic on the various sections of work to be undertaken. Anthony d'Arcy from Catalyst is forming a team to best tackle the job in an orderly manner.

August Update

... And waiting

Last bit of feedback we've received from Crown Lands was July 27th that the application has finally progressed from the Project Officer to the Assessor to complete​ and sign off. It's now August 11th, we're budgeting to invest a million dollars in the project, employ about a dozen people when operational and we've been waiting on Crown Lands since March.

The entire process with Crown Lands is supposed to take between 3 and 5 weeks, according to their own guidelines. 6 months later...

Yep, I'm a little frustrated!

As much as the tarpaulin rig for the leaky roof (see the May update further down) is a thing of rare beauty, it's not going to hang on much longer.

Meanwhile, back at the ranch...

Ok, chill pill consumed and rant over. We have used the past month to assess some more options for the practice and lesson bays and refine what the outdoor areas will look like.

 

The mini-golf course layout has been designed, at a high level, by James Wilcher from 'Golf by Design'. The design can be seen here. Similarly we have drawn up a concept of the outdoor driving range to provide guidance to the engineers in preparation for the DA. As Doc Brown from 'Back to the Future' would say 'Please excuse the crudity of the model...' but my CAD skills are limited! The concept design can be found here.

We're also now planning on a dedicated chipping bay, including an indoor bunker, as well as a dedicated putting bay. The chipping bay will also utilise the Uneekor technology and we are currently assessing techs for the putting bay.

 

July Update

Progress so far...

Without the formal approval we're limited to testing equipment and trying to stem the decay of the auditorium and surrounds. The first test bay is operational and demonstrating that the technology employed is 1st rate and providing an incredible amount of feedback to the golfer.

How good is this!?!?

Originally we expected to rip up the old court synthetic surface and replace with a new one. Thinking it may be an interim step we thought we'd test out a pressure clean of a section of the court to see if it would at least look reasonable until the work to replace the surface commenced. To our amazement, under all of the algae, grime and God knows what the synthetic turf was still in tip top shape. The test section went from an almost concrete-like surface to a fluffy synthetic grass again.

Hat's off to Dave at Blazing Pressure Cleaning for the result. We look forward to you tackling the entire court surface at the end of the month. There will be lots of double takes from the cars driving past at the bright green surface that's coming back to Broadmeadow.

20210601_115353.jpg
20210628_141157.jpg
20210628_141226.jpg

June Update

Twiddling Thumbs...

Seems like there's a lot of "t's to cross and i's to dot" for the sub-lease approval, as soon as we get requests for changes we comply and resubmit immediately. Then it sits there for a few more weeks until something else turns up and we go through the process again.

 

In the meantime, we've had some fun setting up the next prototype bay. A lot of bent nails and statements like; "Shouldn't you have screwed that bit in first?", "That's not going to work" and "Why didn't you tell me that before" and we finally had a bay to trial...

20210510_120037.jpg
20210510_120047.jpg
20210510_120027.jpg
20210525_143209.jpg

May Update

 

Any Day Now...

After a false start with Crown Lands, the correct paperwork was submitted in April and we are now waiting on a response. In the meantime we are stabilising the deterioration in the auditorium as best we can. There are too many leaks to try to plug so the best we can do at this stage is set up tarps to channel rainwater back outside. As soon as we get the Crown Lands approval we will replace the roofing to completely fix the water ingress.

20210319_102556.jpg

April Update

Found it!

To whomever takes over the lease of the auditorium after us, here's a tip. When you're looking to connect the internet service and the technician is trying to located the MDF (The thingy with the wires that makes the interwebs work), it's inside a column in the main bar area. Who knew?!?!

After much wailing and gnashing of teeth looking for the MDF, John climbed into the roof and traced wires from the source in the adjoining building through to the bar area. A conversation ensued along the lines of "It's right below me now", "So am I and there's nothing here", "Open your eyes", "Shut your mouth"...

 

Eventually, a painted over panel on a column gave up its secret and we are connected to the world again.

20210414_153016.jpg
20210414_153003.jpg

March Update

Work to be done

Whenever you hear a building referred to as having "good bones", you know it's not going to be pretty.

The bones on this one then are world class. It's a large area and admittedly fantastic potential but man, there's some work to do!

20201111_144805.jpg
20201111_144847.jpg
20201111_144857.jpg
20201111_144906.jpg
20201111_144933.jpg
20201111_144546.jpg
20201111_144822.jpg
20201111_144922.jpg
20201111_144626.jpg
20201111_150611.jpg
20201111_144930.jpg
20201111_144648.jpg
20201111_144810.jpg
20201111_144926.jpg
20201111_144605.jpg
20201111_150635.jpg
20201111_145753.jpg
20201111_144718.jpg
20201111_144820.jpg
20201111_144754.jpg